How to write an inspection and test plan (ITP) for construction
An inspection and test plan (ITP) sets out what must be checked on a construction job, when the check happens, what counts as a pass, who is responsible and what evidence to keep. Build it from the current contract, drawings and specifications. Give any check that must happen before work continues a named decision maker and a clear release process.

On this page
- What does a construction ITP cover?
- Which information belongs in each row?
- How do hold points and witness points differ?
- How do you build the plan from project documents?
- What does an ITP for a concrete pour look like?
- What happens when an inspection or test fails?
- How does an ITP fit with required building inspections?
- What should you check before issuing an ITP?
- What else do site teams ask about ITPs?
A useful plan helps the site team decide whether the next activity can start. The example below follows one Australian building work package from preparation through a concrete pour and subsequent test results. It uses fictional work areas and drawing references to show how to write the plan. Your project documents supply the actual engineering criteria, testing frequencies and authority to release each stage.
What does a construction ITP cover?
A construction ITP covers each inspection or test needed to establish that a defined piece of work meets its requirements. It links the activity, the reason for checking, the acceptance criteria, the timing, the responsible roles and the result to an identifiable work area or batch. The team can then see which records support a decision long after the work has been covered.
A project quality management plan explains how the project manages quality overall. The ITP turns that system into a sequence for a specific work package. A pre-pour checklist records observations against that sequence. A test report, drawing, inspection record or release can then supply the evidence for a particular row of the plan.
| Document | Question it answers | Example |
|---|---|---|
| Project quality management plan | How does the project manage quality, documents and failures? | The contractor explains who reviews subcontractor quality records and how to deal with a failed test. |
| Inspection and test plan | What must be checked for this work package, by whom and when? | The concrete ITP nominates a hold point before the pour and lists the evidence needed for release. |
| Inspection checklist or test record | What did someone actually see, measure or test in this location? | A dated record shows which slab area was checked, which drawing was used and what was found. |
Start with a scope the people on site can recognise. An ITP called “concrete” could apply to footings, suspended slabs, repairs or all three. An ITP for an identified slab package can deal with exposed reinforcement, trades sharing the same work area and the point when that work will be concealed. Keep general procedures in the quality plan and include the decisions specific to the work in the ITP. The NSW Government quality management guidelines for construction include an ITP guide and checklist in Appendix D for public construction procurement.
Which information belongs in each row?
Each ITP row should tell the person doing the check what to inspect, what result is acceptable, when to check and where to record the decision. Use one row for each distinct decision. Write the location or lot, method, frequency, governing reference, evidence, responsible person and any notice or release requirement where the team can find them during the work.
Separate three things that often end up in a single cell:
- Requirement: the drawing, specification or approval provision that governs the work.
- Acceptance criterion: the specific result required by that provision.
- Evidence: the observation, measurement, test report or signed record that demonstrates the result for the identified work.
A row that says “check reinforcement per drawings” provides a starting point but leaves the person checking to guess which detail to use. A better entry identifies the current structural sheet and detail, records the required values in the checklist or points to a controlled schedule, and says where actual observations go. A person reviewing the record can then trace the result without relying on the original inspector’s memory.
Record the frequency as an instruction people can apply. Examples include each identified pour, each delivery where the specification requires delivery checks, or the locations and frequency defined in the testing schedule. Leave the row open if the governing documents have not resolved the required frequency. Assign someone to obtain the answer before the work reaches the relevant stage.
A “lot” is the defined portion of work represented by an inspection or test result. It might be a stated pour area, a delivery batch or a group of elements defined by the project. Write down the limits on the plan or an attached marked-up drawing. When a report identifies a different lot, reconcile the discrepancy before treating that report as evidence that the current work conforms.
How do hold points and witness points differ?
A hold point stops the affected work from passing a stated stage until the nominated authority releases it. A witness point gives the nominated party notice and an opportunity to see an activity. Check the contract for what happens if the person does not attend. The ITP needs to state who sends notice, who can release a hold and where to record the decision.
| Type of check | What the site team does | What to keep |
|---|---|---|
| Hold point | Complete the required checks and obtain the specified release before proceeding past that point. | Inspection results, unresolved items, scope of release and the authorised decision. |
| Witness point | Give the nominated party the required notice. Proceed if the contract’s conditions are met. | Notice, timing, attendance or decision, and the test or inspection results. |
| Routine inspection or test | Check the work and handle the result under the project’s quality procedure. | Identified checklist, measurements, evidence of corrective action and any retest. |
Queensland Transport and Main Roads publishes the March 2025 edition of MRTS50 Specific Quality System Requirements as a contract specification. Section 8.3 describes written release for a hold point and advance notice for a witness point. The specification also describes when work may proceed after the witness notice period. Use it to understand the difference, then take the notice periods and authority from your own contract. Queensland Transport and Main Roads specifications
Write the point immediately before the work becomes difficult to inspect or reverse. “Hold before placing concrete in Pour P02” is a usable instruction. “Hold for reinforcement” can leave the crew uncertain about whether a review is pending, whether a partial area can proceed, or whether the instruction applies to the whole pour. State the limits of any partial release in the record. An inspection booking, a completed subcontractor checklist and a release are three different events.
How do you build the plan from project documents?
Build the ITP in construction order. Identify what can be checked on delivery, what will become concealed, what needs to be tested during work and what you can assess only afterwards. Trace every decision back to the contract, current drawings, specifications or approval. Brief the people who must do the checks or make the decisions before the relevant work starts.
- Define the package. Record the project, work area, ITP number and current revision. Include a scope drawing if the limits are hard to describe. Check for adjoining work that another contractor will install or cover.
- Find the controlling documents. Gather current drawings, specifications, contract quality requirements and any project approval inspection schedule. Record revisions. Send disagreements between those documents to the person authorised to resolve them.
- Walk through the activities in order. Start with document and material checks. Continue through inspection of accessible work, required releases, tests during the activity, and later results.
- Assign each check and decision. Name the role that checks, the role that is notified, the role that releases any hold, and the person who tells the crew what may start. Add the actual names or contacts in the project’s controlled documents.
- Agree on the evidence. Decide where to keep checklists, marked-up drawings, reports and releases. Use consistent work-area and lot identifiers so those records can be joined later.
- Issue the approved revision and use it. Brief the team and remove superseded copies from use. When a design revision or programme change affects a check already made, identify what needs to be reviewed or repeated.
Look closely at trade interfaces. The formwork crew, reinforcement crew and services trades can each finish their own scope while the combined detail remains unresolved. Ask who checks a service opening against the structural drawings before the concrete goes in. Add that decision when it affects the package, and record who resolves a conflict. Our guide to building defects and how to prevent them explains how gaps in documentation and supervision can contribute to defects.

What does an ITP for a concrete pour look like?
A concrete ITP should track checks before placement, checks during delivery or placement, and any later tests or records the specification requires. In this fictional example, Pour P02 covers the eastern bay on Level 1. The laboratory results become available after placement, so the release to pour is recorded separately from final acceptance of the lot.
| Stage | What this example checks | Who acts and what evidence stays on file |
|---|---|---|
| Documents ready | Confirm Pour P02 boundaries, current structural and services drawings, and the concrete specification. | Project engineer records drawing revisions, accepted changes and the marked-up pour plan. |
| Work ready for inspection | Check the items identified in the project checklist while they are accessible, including reinforcement details and service openings. Refer to the approved drawings for criteria. | Site supervisor and relevant trades record actual observations and file labelled photos for P02. |
| Hold before pour | Confirm that mandatory checks specified for P02 are complete, agreed evidence is available and any item blocking release has been resolved. | The nominated authority records what is released. The supervisor passes the decision to the pour crew. |
| Delivery and testing | Verify the deliveries and arrange any sampling or testing required by the approved testing schedule. Apply a witness point only where the contract specifies it. | The responsible person links each relevant delivery docket and test sample to P02 and files any witness notice. |
| After placement | Review records and available test results against the specification. Resolve and document exceptions before recording lot acceptance. | Project quality lead links laboratory reports and outstanding issues to P02, coordinating any required review. |
Suppose the team finds an undocumented service sleeve before the pour. The supervisor records the location on the marked-up P02 drawing, raises an issue with the project engineer and leaves the affected stage on hold. The engineer obtains an authorised response through the project process, and the team checks the changed detail against the confirmed drawing before recording a release. The fact that the concrete was ordered does not change the inspection criteria or who can make that decision.
Now suppose the delivery docket and sample refer to two different work areas. Reconcile the discrepancy with the people who prepared those records, keeping the original information and any corrected version. Link the corrected evidence to the right lot. Keep the test result outstanding for P02 until the team can show that the result applies to that lot.
What should a release entry say?
One fictional entry might read: “P02, Level 1 east bay, ITP-CON-02 rev B, hold H01. Pre-pour inspection 10:05. Service sleeve issue Q-017 checked against the approved drawing revision and closed. Nominee recorded release at 10:30. Release covers P02 only.” The real project should also identify the person, supporting records and any conditions the release carries.
Before the next activity, ask the supervisor to read the release entry back to the crew in plain English. In this example, only the eastern bay is cleared. Any adjoining bay still awaiting its own decision retains its status. An attached drawing with the boundary marked helps the team apply the decision when areas look similar from the work face.
What happens when an inspection or test fails?
When a check fails, record the actual result, identify the affected work and assign someone to organise the response. Preserve the original evidence and follow the contract’s nonconformance procedure. If the result prevents release of a hold point, keep the affected work at that stage until the authorised party accepts the action and the required recheck.
A nonconformance is a failure to meet an identified requirement. Record which requirement applies, what was found, who was notified and how the affected work is identified. The nominated authority may require rectification, retesting or a documented decision before work can proceed. An authorised decision should remain traceable to its supporting evidence, including any conditions that apply.
Use distinct statuses such as awaiting inspection, failed, awaiting report and released. A missing report is an evidence gap. A report that shows a failed test identifies a different problem. An app or spreadsheet may let someone tick the same box for both, but separate statuses make the action clear at the next handover.
If work is already concealed, tell the responsible project and inspection contacts promptly and document the actual sequence. Ask them what evidence is acceptable and what must be inspected or verified. Do not backdate a check or recreate a signature. The NSW Government construction quality guidelines include controlling nonconforming work and keeping records of corrective actions among the project quality requirements they describe.
How does an ITP fit with required building inspections?
A project ITP can list the statutory or approval inspections that affect the order of work, and it can show their status alongside the contractor’s own checks. Confirm which inspections apply and who may carry them out with the project’s certifier, building surveyor or relevant authority. Record the official inspection result and any decision needed before the next activity.
For example, NSW Government guidance explains that certifiers inspect work at specified stages and outlines the role of the final inspection before an occupation certificate. The inspection regime depends on the jurisdiction and approval. A new team member reading the ITP should see both which internal release the contractor requires and which inspection is part of the approval process. What certifiers do, NSW Government
If you bring an existing plan to a new job, check the building use and class, jurisdiction, approval conditions, certifier’s schedule and contract. Update the plan before issuing it, even when both jobs have similar concrete or waterproofing work. Read our guide to NCC building classifications explained if the class references in the approval paperwork are unfamiliar.
What should you check before issuing an ITP?
An ITP is ready to issue when the site team can apply it to the actual work area without guessing about the required result, the timing or the person who can give clearance. Ask one person who did not write the plan to follow a row from the latest drawing to its evidence and the release decision.
- Scope: Can a supervisor point to the exact lot, room or pour that a record covers?
- Timing: Do checks happen before the evidence disappears or the next activity begins?
- Criteria: Are the governing documents and checkpoints current and clear enough to use?
- Authority: Does the plan say who checks, who receives notice and who authorises release?
- Changes: Can the team see when a revised detail or failed check requires another decision?
- Records: Can someone trace the observations, notices, results and decisions by work area?
Queensland Transport and Main Roads lists CAC052M, Contractor’s Inspection and Test Plan, among its contract administration checklists. It is an additional reference if you need to compare your plan with a public client’s review process. Check the applicability notes before using any external checklist on your project. Queensland Transport and Main Roads standard checklists
Work through the Quality Management and Inspection Test Plans course for structured learning on inspection evidence, roles and handling nonconforming work. The construction short courses collection covers related site and building topics.
What else do site teams ask about ITPs?
Site teams often ask who owns the plan, where to enter a pass result, what to do when someone is absent and how long to keep evidence. Check the project’s contract and quality procedure first. The ITP should turn those requirements into instructions the site team can follow and verify at the work face.
Who writes an inspection and test plan?
The contractor or subcontractor responsible for the work often prepares the ITP, using the contract to confirm who reviews or accepts it. Get input from the person doing the work and the people who will inspect or test it. A plan needs both the contractual criteria and a sequence the team can carry out.
Can an ITP and checklist be in the same file?
Yes, if the project accepts that format and the file clearly distinguishes instructions from completed records. Keep one controlled copy of the blank plan and identify every completed record by lot and date. Preserve whatever version each inspection used so later updates do not silently change the record of earlier work.
Can the crew pour if a witness does not attend?
Check the contract’s notice and proceeding conditions. Some specifications allow work to proceed after proper notice and the end of the notice period. Keep evidence of the notice and carry out the test or inspection required for the activity. A separate hold point or statutory inspection still needs its own decision.
How long should site teams keep completed ITP records?
Apply the retention provisions in the contract, the relevant approval or legislation, and the organisation’s recordkeeping requirements. Identify the handover recipient and format early. File supporting material alongside the ITP so someone can still identify which drawing, test and release supported the result after the original site team has moved on.