A quote that makes money is built from measured quantities, real supplier and subcontractor prices, a full allowance for site costs and business overheads, a deliberate profit margin and a contingency for the risks you are carrying. Most losses come from what was left out — preliminaries, waste, supervision time, overheads — rather than from the rates themselves.
The legal side matters too. Quotes to consumers must show a single total price including GST, residential building laws in some states regulate prime cost items, provisional sums and cost escalation clauses, and an accepted quote can become a binding contract. This guide is general information only; get legal or accounting advice on your own contracts and pricing.
What is the difference between an estimate and a quote?
An estimate is your calculation of what a job will cost you. A quote is the price you offer the client, and it can become part of a binding contract once accepted.
Business Queensland describes an estimate given to a customer as a rough, non-binding guide, and a quote as your statement that you have the information you need to price the work properly. If the customer accepts it, the quote forms part of a legally binding contract. That is why a quote needs a clear scope, clear exclusions and an expiry date.
If you are giving an indicative figure before the design is settled, say clearly in writing that it is an estimate only and will change.
How do you build an estimate that doesn't miss anything?
Work from the documents, not from memory or a square-metre rate. A reliable method looks like this:
- Read everything first. Drawings, specification, engineering, energy assessment, soil report, planning conditions and any site survey. Note anything unclear and ask before you price.
- Take off the quantities. Measure each trade element — concrete, framing, linings, roofing, tiling, finishes — and record where each quantity came from.
- Price materials with waste. Use current supplier prices and add realistic waste and offcut allowances for each material.
- Price labour from productivity. Work out hours from realistic output rates for your crew, then apply your fully loaded labour cost, including super, leave, workers compensation and non-productive time.
- Get subcontractor quotes. Compare them like for like, and read the exclusions closely. A cheap quote that excludes scaffolding or waste removal is not cheap.
- Price the preliminaries. Site establishment, temporary fencing and amenities, scaffolding and edge protection, supervision, cleaning, waste, insurances, permits, inspections and site security.
- Add overheads, contingency and margin, as separate, visible lines in your workings.
Keep the estimate in a structured spreadsheet or estimating system so you can compare it with actual costs at the end of the job. That comparison is what makes your next estimate better.

How should you price overheads and margin?
Overheads are the costs of running the business that do not belong to any one job: office rent, vehicles, software, insurance, accounting, licences, marketing and your own time spent quoting and managing. Work out your annual overheads, then recover them across the work you realistically expect to win in a year — as a percentage of costs, or as a weekly charge for each week a job runs.
Margin is the profit left after all costs, including overheads. It pays for risk, growth and the jobs that go wrong.
Builders often confuse markup with margin, and the gap costs money. A worked example:
- Job cost: $100,000, including overheads.
- Markup of 20%: price of $120,000 before GST.
- Margin on that price: $20,000 ÷ $120,000 = about 16.7%, not 20%.
If you want a true 20% margin, you need to divide cost by 0.8, giving a price of $125,000. Decide which measure your business uses, and use it consistently.
What are contingencies, prime cost items and provisional sums?
These three are often lumped together, but they work differently:
- Contingency is your own allowance for risk inside a fixed price — unknown ground conditions, weather, minor design gaps. It is not shown to the client as an adjustable amount; if it is not used, it becomes profit.
- Prime cost (PC) item is an allowance for an item, such as a fitting or appliance, that the client has not yet selected or whose price is not known when the contract is signed.
- Provisional sum (PS) is an allowance for work that cannot be priced precisely when the contract is signed, such as rock excavation or an air-conditioning installation.
PC items and provisional sums are adjusted to the actual cost, so the contract needs to say how that adjustment and any margin on increases will be calculated.
Residential building laws in some states regulate them closely. In Victoria, under the Domestic Building Contracts Act 1995:
- Section 20. The builder warrants that any provisional sum has been calculated with reasonable care and skill, taking account of the information reasonably available when the contract is made, including the nature and location of the site.
- Section 21. A builder must not enter into a domestic building contract with a PC item or provisional sum that is less than the reasonable cost of supplying the item or carrying out the work.
- Section 22. A major domestic building contract must include a separate schedule for each item or sum, with a description, a cost breakdown showing at least estimated quantities and unit costs, and how any amount charged above the actual increase will be worked out.
- Section 23. The builder must give the owner copies of invoices or receipts showing the cost of PC items and provisional sums.
Other states have their own rules for residential contracts, so check the home building legislation where you work. Deliberately low allowances that make a quote look cheaper are exactly what these laws target.
How do you quote GST correctly?
When you quote consumers, quote the total price including GST. Under the component pricing rule in section 48 of the Australian Consumer Law, if you state part of a price you must also state a single total price, at least as prominently, that includes any tax, duty, fee or charge such as GST, according to the ACCC.
Good practice is to show the total including GST as the headline figure, with the GST amount shown in the breakdown. Quoting ex-GST figures to a home owner invites disputes.
PC items and provisional sums should also state clearly whether they include GST and whether your margin is included, so the adjustment at the end is not argued over. Thresholds for residential contracts are also usually GST-inclusive: in New South Wales, for example, the NSW Government says a written contract is required for residential building work over $5,000 including GST, with a more detailed contract over $20,000.
How long should a quote stay valid?
Always include an expiry date. Business Queensland warns that material costs can increase quickly, and without an expiry date you may have to honour a quote that loses you money.
The right period depends on how volatile your prices are and how long your suppliers will hold theirs. Match your validity period to your suppliers’ and subcontractors’ quote periods, and state that the price will be reviewed if the client accepts after the expiry date or if the start date is delayed.
Also state in the quote:
- What it is based on. Drawing and specification revision numbers.
- What is excluded. Rock, contamination, authority fees, landscaping — whatever you have not priced.
- Assumptions. Site access, working hours, and the start date and duration you have allowed for.
Can you include a cost escalation clause?
On commercial work, rise and fall clauses are a matter for negotiation in the contract. On residential work, the law may restrict them.
In Victoria, section 15 of the Domestic Building Contracts Act 1995 says a builder must not enter into a domestic building contract with a cost escalation clause unless the contract price is more than $500,000 (or a higher amount set by regulation), or the clause is in a form approved by the Director. Even then, the clause is void unless, before the contract was signed, the owner was given an approved notice explaining it and signed or initialled next to the clause. The definition excludes increases for unforeseeable changes to government taxes and charges, and adjustments to PC items and provisional sums.
Where an escalation clause is not available, your protection is careful pricing: a short quote validity period, an allowance for expected price movement over the job, and early purchasing of volatile materials. Our guide to variations and extensions of time covers how to price changes once the job is under way, and building contract basics covers what to check before you sign.

Estimating and quoting checklist
- Documents read in full. Drawings, specification, engineering and reports, with questions asked.
- Quantities measured. Each element taken off and traceable to a drawing.
- Materials priced with waste. Current supplier prices, realistic waste factors.
- Labour priced from productivity. Fully loaded labour cost, not just the hourly wage.
- Subcontractor quotes compared. Like for like, with exclusions read.
- Preliminaries priced. Scaffolding, fencing, amenities, supervision, waste, insurance and permits.
- Overheads, contingency and margin. Separate lines, using margin and markup correctly.
- PC items and provisional sums. Realistic, itemised, and compliant with state law.
- GST-inclusive total. Single total price shown prominently for consumers.
- Expiry date and exclusions. Stated clearly on the quote.
For the bigger picture on costs, cash flow and licensing, see starting a building business in Australia.
Price every job to make money
CPD-accredited online courses on estimating, quoting, cost control and construction finance, each with an assessment and a certificate.
- Estimating, Quoting and Construction Cost Control View course →
- Finance Fundamentals for Building and Construction Businesses View course →
- Running a Small Building and Construction Business View course →
- Contract Administration: Variations, Claims and Extensions of Time View course →
- Basic Contract Law for Building and Construction View course →
- Managing Risk and Reducing Disputes in Construction View course →
Frequently asked questions
Is a quote legally binding?
It can be. Once a client accepts a quote, it can form part of a legally binding contract, which is why it needs a clear scope, exclusions and an expiry date. An estimate clearly labelled as an indication only is generally not intended to bind you to the price.
What is the difference between markup and margin?
Markup is profit as a percentage of cost; margin is profit as a percentage of the selling price. A 20% markup on a $100,000 cost gives a $120,000 price, but the margin on that price is only about 16.7%.
Do I have to include GST in my quote?
When quoting consumers, the ACCC says the total price must include GST and any other charges, shown as a single figure at least as prominently as any part price. Showing the GST amount separately in the breakdown is good practice.
What is a provisional sum?
A provisional sum is an allowance for work that cannot be priced precisely when the contract is signed. It is adjusted to the actual cost. In Victoria, a builder must not include a provisional sum that is less than the reasonable cost of the work.
How long should a building quote be valid for?
There is no single legal period. Set an expiry date that matches how long your suppliers and subcontractors will hold their prices, and state that the price will be reviewed if accepted late or if the start is delayed.
Can I put a rise and fall clause in a home building contract?
It depends on the state. In Victoria, a cost escalation clause is only allowed in a domestic building contract over $500,000 or in an approved form, and is void unless the owner received an approved notice and initialled the clause. Check the law in your state.
Sources and further reading
- Victorian Legislation — Domestic Building Contracts Act 1995 (authorised version 092), ss 15, 20–23
- Consumer Affairs Victoria — Changing a domestic building contract price
- ACCC — Advertising and selling guide: component pricing
- Business Queensland — Preparing a business quote
- NSW Government — Guide to providing home building contracts
- Consumer Affairs Victoria — Giving quotes: tradespeople and small works